    PracticePMI PMP®PMI PMP Practice Exam 6Question 65
    Hard1 markMultiple Choice
    Task 16: Ensure knowledge transfer for project continuityknowledge transferteam transitionsarchitectural knowledgeproject continuity

    PMP · Question 65 · Task 16: Ensure knowledge transfer for project continuity

    A project manager is preparing for a planned team member transition where a senior architect will be leaving the project in three weeks. The architect has been working on critical system design components and has significant knowledge about integration requirements and technical decisions. What should the project manager do FIRST?

    Answer options:

    A.

    Work with the departing architect to identify critical knowledge areas and create a structured knowledge transfer plan

    B.

    Ask the architect to document all their design decisions and technical rationale

    C.

    Schedule intensive training sessions between the architect and the development team

    D.

    Have the architect create detailed technical specifications for all their work areas

    How to approach this question

    Look for systematic approaches that identify what critical knowledge needs to be transferred and create structured plans for effective transfer.

    Full Answer

    A.Work with the departing architect to identify critical knowledge areas and create a structured knowledge transfer plan✓ Correct
    A
    Effective knowledge transfer for critical roles requires systematic identification of the most important knowledge areas and structured planning to ensure comprehensive and effective transfer to the right people.

    Common mistakes

    Relying on general documentation, assuming knowledge transfer will happen naturally through training, or not focusing on the most critical knowledge areas.
    Question 64All questionsQuestion 66

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →