Hard1 markMultiple Choice
Task 17: Plan and manage project/phase closure or transitionsproject closuretransition planningoperations readinessdeliverable handover

PMP · Question 66 · Task 17: Plan and manage project/phase closure or transitions

A project is approaching completion, and the project manager needs to transition the deliverables to the operations team. The operations team has expressed concerns about their readiness to support the new system, and some final integration testing is still in progress. What should the project manager do FIRST?

Answer options:

A.

Complete all testing and project activities before beginning any transition activities

B.

Assess the operations team's specific readiness concerns and develop a transition plan that addresses them

C.

Schedule the transition for after all project deliverables are completely finished

D.

Provide the operations team with comprehensive project documentation for their review

How to approach this question

Look for approaches that assess the receiving team's specific readiness concerns and address them through targeted transition planning.

Full Answer

B.Assess the operations team's specific readiness concerns and develop a transition plan that addresses them✓ Correct
B
Successful project transitions require assessing the receiving team's specific readiness concerns and developing transition plans that address those concerns to ensure effective handover and ongoing support.

Common mistakes

Focusing only on project completion without considering receiving team readiness, assuming documentation is sufficient for transition support, or not addressing specific concerns.

Practice the full PMI PMP Practice Exam 6

100 questions · hints · full answers · grading

More questions from this exam