Hard1 markMultiple Choice
PMP · Question 71 · Task 1: Manage conflict
During a retrospective, two team members engage in a heated argument about the root cause of a recurring technical issue. The argument is becoming personal and other team members are becoming uncomfortable. What should the project manager do FIRST to manage this conflict?
During a retrospective, two team members engage in a heated argument about the root cause of a recurring technical issue. The argument is becoming personal and other team members are becoming uncomfortable. What should the project manager do FIRST to manage this conflict?
Answer options:
A.
Immediately end the retrospective and schedule individual meetings with both team members
B.
Intervene to refocus the discussion on the technical issue rather than personal positions
C.
Ask the Scrum Master to handle the conflict since it's occurring during a Scrum ceremony
D.
Let the team members work through the conflict themselves to build team resilience
How to approach this question
Look for interventions that redirect conflict from personal to substantive issues while maintaining team psychological safety.
Full Answer
B.Intervene to refocus the discussion on the technical issue rather than personal positions✓ Correct
Effective conflict management involves intervening when conflicts become personal to redirect focus back to the substantive issues that need to be resolved, maintaining team psychological safety.
Common mistakes
Avoiding conflict intervention, delegating responsibility inappropriately, or allowing personal conflicts to escalate and damage team dynamics.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert