PMP · Question 75 · Task 5: Ensure team members/stakeholders are adequately trained
A project team is transitioning from traditional waterfall to agile methodology. Team members have varying levels of agile experience, with some having no agile background and others having worked on agile projects before. What should the project manager do FIRST to ensure adequate training?
A project team is transitioning from traditional waterfall to agile methodology. Team members have varying levels of agile experience, with some having no agile background and others having worked on agile projects before. What should the project manager do FIRST to ensure adequate training?
Answer options:
Conduct a comprehensive skills assessment to identify specific agile competency gaps for each team member
Provide standardized agile training to all team members to ensure consistent knowledge
Pair team members with agile experience with those who are new to agile practices
Start with basic agile principles and gradually introduce more advanced practices over time
How to approach this question
Full Answer
Common mistakes