Hard1 markMultiple Choice
Task 5: Ensure team members/stakeholders are adequately trainedtraining needs assessmentagile transitionindividual competency gapsdiverse experience levels

PMP · Question 75 · Task 5: Ensure team members/stakeholders are adequately trained

A project team is transitioning from traditional waterfall to agile methodology. Team members have varying levels of agile experience, with some having no agile background and others having worked on agile projects before. What should the project manager do FIRST to ensure adequate training?

Answer options:

A.

Conduct a comprehensive skills assessment to identify specific agile competency gaps for each team member

B.

Provide standardized agile training to all team members to ensure consistent knowledge

C.

Pair team members with agile experience with those who are new to agile practices

D.

Start with basic agile principles and gradually introduce more advanced practices over time

How to approach this question

Look for systematic approaches that assess current state and individual needs before determining training solutions, especially with diverse experience levels.

Full Answer

A.Conduct a comprehensive skills assessment to identify specific agile competency gaps for each team member✓ Correct
A
Effective training programs for teams with diverse experience levels start with comprehensive assessment of individual competencies to identify specific gaps, ensuring training resources are used efficiently and address actual needs.

Common mistakes

Assuming uniform training needs, providing generic training that doesn't address individual gaps, or implementing solutions without proper assessment of current capabilities.

Practice the full PMI PMP Practice Exam 6

100 questions · hints · full answers · grading

More questions from this exam