    PracticePMI PMP®PMI PMP Practice Exam 6Question 74
    Hard1 markMultiple Choice
    Task 4: Empower team members and stakeholdersempowermentdecision-making authoritydata analyticsbounded autonomy

    PMP · Question 74 · Task 4: Empower team members and stakeholders

    A highly skilled team member with expertise in data analytics asks for authority to make decisions about data model design and analytics algorithms without requiring approval for each decision. They have consistently delivered excellent results and other team members respect their expertise. What should the project manager do?

    Answer options:

    A.

    Grant complete decision-making authority for all data-related aspects of the project

    B.

    Define clear boundaries for data analytics decisions and establish regular alignment check-ins

    C.

    Maintain current approval processes to ensure consistency with overall project architecture

    D.

    Require documentation of all decisions for post-implementation review and approval

    How to approach this question

    Look for balanced approaches that provide autonomy appropriate to competence while maintaining necessary alignment and coordination with the broader project.

    Full Answer

    B.Define clear boundaries for data analytics decisions and establish regular alignment check-ins✓ Correct
    B
    Effective empowerment provides decision-making authority appropriate to the person's competence and the impact of their decisions, with clear boundaries and regular alignment to ensure coordination with the broader project.

    Common mistakes

    Granting complete autonomy without boundaries, maintaining excessive control that doesn't recognize expertise, or creating review processes that don't provide real empowerment.
    Question 73All questionsQuestion 75

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →