    PracticePMI PMP®PMI PMP Practice Exam 6Question 79
    Hard1 markMultiple Choice
    Task 9: Collaborate with stakeholdersstakeholder managementrelationship buildingtrust rebuildingstakeholder collaboration

    PMP · Question 79 · Task 9: Collaborate with stakeholders

    A key stakeholder who was initially supportive of the project has become increasingly critical and is publicly questioning project decisions and progress. This is affecting team morale and other stakeholder confidence in the project. What should the project manager do FIRST?

    Answer options:

    A.

    Address the stakeholder's concerns publicly to demonstrate transparency and project confidence

    B.

    Document the stakeholder's behavior and escalate to the project sponsor for intervention

    C.

    Schedule a private meeting with the stakeholder to understand their concerns and work to rebuild trust and alignment

    D.

    Limit the stakeholder's access to project information to prevent further public criticism

    How to approach this question

    Look for collaborative approaches that seek to understand stakeholder concerns and rebuild relationships rather than confrontational, avoidance, or restrictive strategies.

    Full Answer

    C.Schedule a private meeting with the stakeholder to understand their concerns and work to rebuild trust and alignment✓ Correct
    Effective stakeholder collaboration requires understanding changing stakeholder positions and working proactively to rebuild trust and alignment when relationships deteriorate, rather than avoiding or confronting the issue.

    Common mistakes

    Choosing confrontational approaches, premature escalation, avoidance strategies, or restrictive measures that don't address the underlying relationship and trust issues.
    Question 78All questionsQuestion 80

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard