Hard1 markMultiple Choice
Task 4: Engage stakeholdersstakeholder analysisstakeholder categorizationtailored engagement strategiesdiverse stakeholders

PMP · Question 88 · Task 4: Engage stakeholders

A project manager is analyzing stakeholders for a new enterprise software implementation that will affect multiple departments, external partners, regulatory bodies, and end users. The analysis reveals highly diverse stakeholder groups with varying levels of influence, interest, and engagement requirements. What should the project manager do FIRST?

Answer options:

A.

Create a comprehensive communication plan that provides consistent information to all stakeholder groups

B.

Systematically categorize stakeholders based on their power, interest, influence levels, and engagement requirements to develop tailored strategies

C.

Focus engagement efforts primarily on the regulatory bodies and executive sponsors since they have the most power

D.

Schedule regular meetings with all stakeholder groups to ensure equal treatment and consistent communication

How to approach this question

Look for systematic approaches that recognize stakeholder diversity and develop appropriate engagement strategies for each category based on their specific characteristics.

Full Answer

B.Systematically categorize stakeholders based on their power, interest, influence levels, and engagement requirements to develop tailored strategies✓ Correct
B
Effective stakeholder engagement for diverse groups requires systematic categorization of stakeholders followed by development of tailored engagement strategies appropriate for each group's power, interest, influence, and specific requirements.

Common mistakes

Using one-size-fits-all approaches, focusing only on high-power stakeholders, treating all stakeholders identically, or not recognizing the need for different engagement strategies.

Practice the full PMI PMP Practice Exam 6

100 questions · hints · full answers · grading

More questions from this exam