For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 6Question 87
    Hard1 markMultiple Choice
    Task 3: Assess and manage riskstechnical riskauthentication servicesspike testingagile risk management

    PMP · Question 87 · Task 3: Assess and manage risks

    During iteration planning, the team identifies a new technical risk: the third-party authentication service they planned to integrate may not handle the expected user load during peak usage periods, potentially causing system failures. This could impact the upcoming release. What should the project manager do FIRST?

    Answer options:

    A.

    Add the risk to the risk register and schedule detailed analysis and planning for the next iteration

    B.

    Remove the authentication service integration from the current iteration to avoid the risk entirely

    C.

    Conduct a technical spike to test the authentication service's capacity limits and identify potential solutions or alternatives

    D.

    Escalate the risk to the product owner for a scope and priority decision

    How to approach this question

    Look for approaches that provide quick technical risk assessment and solution exploration, especially in agile contexts where rapid feedback and testing are valuable.

    Full Answer

    C.Conduct a technical spike to test the authentication service's capacity limits and identify potential solutions or alternatives✓ Correct
    C
    In agile environments, conducting technical spikes to quickly assess technical risks through testing and explore solutions provides the rapid feedback needed for informed decision-making about technical integration risks.

    Common mistakes

    Delaying technical risk assessment, making premature scope decisions without technical information, or escalating without sufficient technical analysis and solution exploration.
    Question 86All questionsQuestion 88

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →