    PracticePMI PMP®PMI PMP Practice Exam 6Question 86
    Hard1 markMultiple Choice
    Task 2: Manage communicationscommunication managementstakeholder communicationinformation consistencycommunication protocols

    PMP · Question 86 · Task 2: Manage communications

    A project manager discovers that different stakeholder groups are receiving conflicting information about project status from various team members, leading to confusion, eroded stakeholder confidence, and conflicting expectations. What should the project manager do FIRST?

    Answer options:

    A.

    Establish a centralized communication system with a single source of truth and define clear communication protocols and responsibilities

    B.

    Send an immediate clarification email to all stakeholders with the correct project status and information

    C.

    Restrict team members from communicating directly with stakeholders without prior approval

    D.

    Schedule individual meetings with each stakeholder group to clarify the current situation and expectations

    How to approach this question

    Look for systematic approaches that address the root cause of communication problems rather than just treating symptoms or creating restrictions.

    Full Answer

    A.Establish a centralized communication system with a single source of truth and define clear communication protocols and responsibilities✓ Correct
    Effective communication management requires establishing systematic processes with centralized information sources and clear communication protocols to prevent conflicting information from reaching stakeholders.

    Common mistakes

    Focusing on immediate fixes rather than systematic solutions, restricting communication without establishing proper processes, or treating symptoms rather than addressing root causes of communication problems.
    Question 85All questionsQuestion 87

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →