PMP · Question 86 · Task 2: Manage communications
A project manager discovers that different stakeholder groups are receiving conflicting information about project status from various team members, leading to confusion, eroded stakeholder confidence, and conflicting expectations. What should the project manager do FIRST?
A project manager discovers that different stakeholder groups are receiving conflicting information about project status from various team members, leading to confusion, eroded stakeholder confidence, and conflicting expectations. What should the project manager do FIRST?
Answer options:
Establish a centralized communication system with a single source of truth and define clear communication protocols and responsibilities
Send an immediate clarification email to all stakeholders with the correct project status and information
Restrict team members from communicating directly with stakeholders without prior approval
Schedule individual meetings with each stakeholder group to clarify the current situation and expectations