    PracticePMI PMP®PMI PMP Practice Exam 6Question 85
    Hard1 markMultiple Choice
    Task 1: Execute project with the urgency required to deliver business valuebusiness valueMVPcompetitive advantagevalue-based decisions

    PMP · Question 85 · Task 1: Execute project with the urgency required to deliver business value

    A software development project has an opportunity to deliver a minimum viable product (MVP) six weeks ahead of schedule, which could provide significant competitive advantage and early revenue generation. However, this would require descoping some planned features that stakeholders consider important. What should the project manager do FIRST?

    Answer options:

    A.

    Proceed with the MVP delivery since early market entry and revenue generation provide clear competitive advantage

    B.

    Conduct a comprehensive business value analysis of early delivery versus the value of the descoped features with key stakeholders

    C.

    Maintain the original scope and schedule to ensure all planned features are delivered as committed to stakeholders

    D.

    Ask the development team to work additional hours to deliver all features on the accelerated timeline

    How to approach this question

    Look for approaches that focus on systematic business value analysis and stakeholder involvement in value-based decisions rather than unilateral decisions.

    Full Answer

    B.Conduct a comprehensive business value analysis of early delivery versus the value of the descoped features with key stakeholders✓ Correct
    B
    Delivering business value with urgency requires systematic analysis of trade-offs between early delivery benefits and feature completeness, involving stakeholders in comprehensive value-based decision making.

    Common mistakes

    Making unilateral decisions about scope changes, rigidly adhering to original plans without considering value opportunities, or risking team sustainability without proper analysis.
    Question 84All questionsQuestion 86

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →