PMP · Question 92 · Task 8: Plan and manage scope
During sprint planning, the product owner presents several new high-priority user stories that emerged from recent customer feedback. The development team expresses concern that adding these stories will impact their ability to complete previously committed work and maintain sustainable pace. What should the project manager do FIRST?
During sprint planning, the product owner presents several new high-priority user stories that emerged from recent customer feedback. The development team expresses concern that adding these stories will impact their ability to complete previously committed work and maintain sustainable pace. What should the project manager do FIRST?
Answer options:
Add the new stories to the sprint since they represent important customer feedback and are high priority
Reject the new stories since they weren't in the original sprint planning and would disrupt commitments
Facilitate a discussion about team capacity, business priorities, and sustainable approaches to managing the new requirements
Ask the team to work additional hours to accommodate both the original commitments and new high-priority work
How to approach this question
Full Answer
Common mistakes