PMP · Question 93 · Task 9: Integrate project planning activities
A project manager is integrating plans from multiple workstreams for a large digital transformation involving cloud migration, process automation, and organizational change. During integration, they discover resource conflicts, timeline dependencies that weren't identified, and gaps that could delay business value delivery. What should the project manager do FIRST?
Answer options:
Conduct a comprehensive analysis of all conflicts, dependencies, and gaps to understand their collective impact on business value delivery
Prioritize the cloud migration workstream since it enables the other workstreams and adjust others accordingly
Request additional resources and budget to resolve all identified conflicts and gaps
Escalate the integration issues to the transformation steering committee for immediate resolution