    PracticePMI PMP®PMI PMP Practice ExamQuestion 30
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentEthics

    PMP · Question 30 · Task 1: Plan and manage project compliance

    A project manager is leading a project to launch a new product. The marketing director (a key stakeholder) is pushing to launch early to beat a competitor, but the product has not passed final safety testing. What is the project manager's ethical responsibility?

    Answer options:

    A.

    Refuse to launch until safety testing is passed, citing the PMI Code of Ethics regarding public safety.

    B.

    Launch the product with a warning label to mitigate liability.

    C.

    Follow the marketing director's instructions as they are the senior stakeholder.

    D.

    Launch a limited beta version to a small group.

    How to approach this question

    PMI Code of Ethics: Responsibility, Respect, Fairness, Honesty. Safety is paramount.

    Full Answer

    A.Refuse to launch until safety testing is passed, citing the PMI Code of Ethics regarding public safety.✓ Correct
    A
    Professional Responsibility. The PM has a duty to the public and safety that overrides stakeholder pressure.

    Common mistakes

    Yielding to authority (C) when it violates ethics.
    Question 29All questionsQuestion 31

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →