For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 31
    Hard1 markMultiple Choice
    Task 1: Execute project with urgencyProcessAgileKanban

    PMP · Question 31 · Task 1: Execute project with urgency

    In a hybrid project, the project manager uses a Kanban board to track work. The board shows a large buildup of items in the 'Testing' column, while the 'Development' column is empty. What does this indicate, and what should the PM do?

    Answer options:

    A.

    The developers are too fast; tell them to slow down.

    B.

    The testers are lazy; replace them.

    C.

    There is a bottleneck in Testing; work with the team to swarm on testing or set Work In Progress (WIP) limits to prevent new work from starting.

    D.

    Add more columns to the board to spread out the work.

    How to approach this question

    Analyze the Flow. Pile up = Bottleneck. Solution = Swarm or Limit WIP.

    Full Answer

    C.There is a bottleneck in Testing; work with the team to swarm on testing or set Work In Progress (WIP) limits to prevent new work from starting.✓ Correct
    Task 1 (Execute with urgency/value). Flow management is key. A bottleneck restricts value delivery. The team should collaborate to clear it.

    Common mistakes

    Ignoring the bottleneck or adding more work.
    Question 30All questionsQuestion 32

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →