Hard1 markMultiple Choice
PMP · Question 31 · Task 1: Execute project with urgency
In a hybrid project, the project manager uses a Kanban board to track work. The board shows a large buildup of items in the 'Testing' column, while the 'Development' column is empty. What does this indicate, and what should the PM do?
In a hybrid project, the project manager uses a Kanban board to track work. The board shows a large buildup of items in the 'Testing' column, while the 'Development' column is empty. What does this indicate, and what should the PM do?
Answer options:
A.
The developers are too fast; tell them to slow down.
B.
The testers are lazy; replace them.
C.
There is a bottleneck in Testing; work with the team to swarm on testing or set Work In Progress (WIP) limits to prevent new work from starting.
D.
Add more columns to the board to spread out the work.
How to approach this question
Analyze the Flow. Pile up = Bottleneck. Solution = Swarm or Limit WIP.
Full Answer
C.There is a bottleneck in Testing; work with the team to swarm on testing or set Work In Progress (WIP) limits to prevent new work from starting.✓ Correct
C
Task 1 (Execute with urgency/value). Flow management is key. A bottleneck restricts value delivery. The team should collaborate to clear it.
Common mistakes
Ignoring the bottleneck or adding more work.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert