PMP · Question 31 · Task 1: Execute project with urgency
In a hybrid project, the project manager uses a Kanban board to track work. The board shows a large buildup of items in the 'Testing' column, while the 'Development' column is empty. What does this indicate, and what should the PM do?
Answer options:
The developers are too fast; tell them to slow down.
The testers are lazy; replace them.
There is a bottleneck in Testing; work with the team to swarm on testing or set Work In Progress (WIP) limits to prevent new work from starting.
Add more columns to the board to spread out the work.
114 questions · hints · full answers · grading