Hard1 markMultiple Choice

PMP · Question 32 · Task 15: Manage project issues

A project manager is reviewing the risk register and notices a risk with a high probability and high impact: 'Vendor delay'. The response plan is 'Mitigate'. However, the vendor has just announced a strike, making the delay 100% certain. What should the project manager do?

Answer options:

A.

Leave it in the risk register and monitor it.

B.

Convert the risk to an issue, execute the contingency plan (if any), and update the issue log.

C.

Perform a qualitative risk analysis again.

D.

Fire the vendor immediately.

How to approach this question

Risk = Uncertain. Issue = Certain. Transition from Risk Mgmt to Issue Mgmt.

Full Answer

B.Convert the risk to an issue, execute the contingency plan (if any), and update the issue log.✓ Correct
B
Task 15 (Manage project issues). When a risk materializes, it moves to the Issue Log. The PM executes the planned response (contingency).

Common mistakes

Keeping it in the risk register.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam