Hard1 markMultiple Choice
PMP · Question 32 · Task 15: Manage project issues
A project manager is reviewing the risk register and notices a risk with a high probability and high impact: 'Vendor delay'. The response plan is 'Mitigate'. However, the vendor has just announced a strike, making the delay 100% certain. What should the project manager do?
A project manager is reviewing the risk register and notices a risk with a high probability and high impact: 'Vendor delay'. The response plan is 'Mitigate'. However, the vendor has just announced a strike, making the delay 100% certain. What should the project manager do?
Answer options:
A.
Leave it in the risk register and monitor it.
B.
Convert the risk to an issue, execute the contingency plan (if any), and update the issue log.
C.
Perform a qualitative risk analysis again.
D.
Fire the vendor immediately.
How to approach this question
Risk = Uncertain. Issue = Certain. Transition from Risk Mgmt to Issue Mgmt.
Full Answer
B.Convert the risk to an issue, execute the contingency plan (if any), and update the issue log.✓ Correct
B
Task 15 (Manage project issues). When a risk materializes, it moves to the Issue Log. The PM executes the planned response (contingency).
Common mistakes
Keeping it in the risk register.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert