PMP · Question 39 · Task 2: Manage communications
A project manager is preparing the communications management plan. The project has a large number of stakeholders with varying levels of interest and power. Which tool should the PM use to determine the appropriate communication frequency and method for each stakeholder?
Answer options:
Organizational Chart
Stakeholder Engagement Assessment Matrix and Power/Interest Grid
Resource Histogram
Ishikawa Diagram