Hard1 markMultiple Choice
PMP · Question 39 · Task 2: Manage communications
A project manager is preparing the communications management plan. The project has a large number of stakeholders with varying levels of interest and power. Which tool should the PM use to determine the appropriate communication frequency and method for each stakeholder?
A project manager is preparing the communications management plan. The project has a large number of stakeholders with varying levels of interest and power. Which tool should the PM use to determine the appropriate communication frequency and method for each stakeholder?
Answer options:
A.
Organizational Chart
B.
Stakeholder Engagement Assessment Matrix and Power/Interest Grid
C.
Resource Histogram
D.
Ishikawa Diagram
How to approach this question
Input: Stakeholder Analysis. Output: Comms Plan.
Full Answer
B.Stakeholder Engagement Assessment Matrix and Power/Interest Grid✓ Correct
B
Task 2 (Manage communications). Communication planning is based on Stakeholder Analysis (Task 4). The Power/Interest grid dictates the strategy (Manage Closely vs Monitor), which dictates the communication frequency.
Common mistakes
Thinking Comms Plan is generic. It must be tailored via analysis.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert