For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 39
    Hard1 markMultiple Choice
    Task 2: Manage communicationsProcessCommunications

    PMP · Question 39 · Task 2: Manage communications

    A project manager is preparing the communications management plan. The project has a large number of stakeholders with varying levels of interest and power. Which tool should the PM use to determine the appropriate communication frequency and method for each stakeholder?

    Answer options:

    A.

    Organizational Chart

    B.

    Stakeholder Engagement Assessment Matrix and Power/Interest Grid

    C.

    Resource Histogram

    D.

    Ishikawa Diagram

    How to approach this question

    Input: Stakeholder Analysis. Output: Comms Plan.

    Full Answer

    B.Stakeholder Engagement Assessment Matrix and Power/Interest Grid✓ Correct
    Task 2 (Manage communications). Communication planning is based on Stakeholder Analysis (Task 4). The Power/Interest grid dictates the strategy (Manage Closely vs Monitor), which dictates the communication frequency.

    Common mistakes

    Thinking Comms Plan is generic. It must be tailored via analysis.
    Question 38All questionsQuestion 40

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →