Hard1 markMultiple Choice
Task 2: Manage communicationsProcessCommunications

PMP · Question 39 · Task 2: Manage communications

A project manager is preparing the communications management plan. The project has a large number of stakeholders with varying levels of interest and power. Which tool should the PM use to determine the appropriate communication frequency and method for each stakeholder?

Answer options:

A.

Organizational Chart

B.

Stakeholder Engagement Assessment Matrix and Power/Interest Grid

C.

Resource Histogram

D.

Ishikawa Diagram

How to approach this question

Input: Stakeholder Analysis. Output: Comms Plan.

Full Answer

B.Stakeholder Engagement Assessment Matrix and Power/Interest Grid✓ Correct
B
Task 2 (Manage communications). Communication planning is based on Stakeholder Analysis (Task 4). The Power/Interest grid dictates the strategy (Manage Closely vs Monitor), which dictates the communication frequency.

Common mistakes

Thinking Comms Plan is generic. It must be tailored via analysis.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam