    PracticePMI PMP®PMI PMP Practice ExamQuestion 40
    Hard1 markMultiple Choice
    Task 15: Manage project issuesProcessIssues

    PMP · Question 40 · Task 15: Manage project issues

    A project manager is leading a software project. The team discovers that a third-party library they planned to use is no longer supported. This is a new issue. What should the PM do FIRST?

    Answer options:

    A.

    Update the project schedule to reflect the delay.

    B.

    Inform the sponsor.

    C.

    Log the issue and work with the team to identify alternatives and assess impact.

    D.

    Continue using the unsupported library to save time.

    How to approach this question

    Issue happens -> Log -> Analyze -> Solve.

    Full Answer

    C.Log the issue and work with the team to identify alternatives and assess impact.✓ Correct
    Task 15 (Manage project issues). The first step is always to capture the issue and engage the team to find a solution.

    Common mistakes

    Escalating immediately (B) or updating plans without analysis (A).
    Question 39All questionsQuestion 41

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →