PMP · Question 41 · Task 8: Plan and manage scope
A project manager is working on a project with a fixed deadline. The team realizes they cannot complete all the scope by the deadline. The sponsor says the deadline is immovable, but some features are less important. Which approach should the PM use?
Answer options:
Crashing the schedule by adding more resources.
Prioritize the backlog (MoSCoW) and descoping the low-priority features.
Fast-tracking the schedule by running tasks in parallel.
Extend the deadline.
114 questions · hints · full answers · grading