For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 41
    Hard1 markMultiple Choice
    Task 8: Plan and manage scopeProcessScopeSchedule

    PMP · Question 41 · Task 8: Plan and manage scope

    A project manager is working on a project with a fixed deadline. The team realizes they cannot complete all the scope by the deadline. The sponsor says the deadline is immovable, but some features are less important. Which approach should the PM use?

    Answer options:

    A.

    Crashing the schedule by adding more resources.

    B.

    Prioritize the backlog (MoSCoW) and descoping the low-priority features.

    C.

    Fast-tracking the schedule by running tasks in parallel.

    D.

    Extend the deadline.

    How to approach this question

    Identify the constraints. Time = Fixed. Scope = Flexible. Action = Cut Scope.

    Full Answer

    B.Prioritize the backlog (MoSCoW) and descoping the low-priority features.✓ Correct
    B
    Task 8 (Manage scope). In fixed-date projects (like Agile), scope is the variable constraint. Prioritization ensures value is delivered even if full scope isn't.

    Common mistakes

    Trying to force the work (Crashing/Fast-tracking) when the sponsor has already offered scope flexibility.
    Question 40All questionsQuestion 42

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →