PMP · Question 04 · Task 1: Manage conflict
A project manager discovers that a vendor has been contacting team members directly to offer gifts in exchange for favorable reviews of their deliverables. This violates the company's code of conduct. What should the project manager do FIRST?
Answer options:
Immediately terminate the vendor's contract.
Ask the team members to return the gifts and continue working.
Follow the organization's policy for reporting ethical violations and document the evidence.
Negotiate with the vendor to stop the behavior.