    PracticePMI PMP®PMP People Domain Practice ExamQuestion 04
    Hard1 markMultiple Choice
    Task 1: Manage conflictConflict ManagementEthics

    PMP · Question 04 · Task 1: Manage conflict

    A project manager discovers that a vendor has been contacting team members directly to offer gifts in exchange for favorable reviews of their deliverables. This violates the company's code of conduct. What should the project manager do FIRST?

    Answer options:

    A.

    Immediately terminate the vendor's contract.

    B.

    Ask the team members to return the gifts and continue working.

    C.

    Follow the organization's policy for reporting ethical violations and document the evidence.

    D.

    Negotiate with the vendor to stop the behavior.

    How to approach this question

    In ethical scenarios, look for the answer that involves following policy, reporting, and gathering facts before taking irreversible action.

    Full Answer

    C.Follow the organization's policy for reporting ethical violations and document the evidence.✓ Correct
    C
    The PM must adhere to the code of ethics and organizational policies. Reporting the violation ensures it is handled legally and procedurally correctly.

    Common mistakes

    Acting as judge and jury (A) without following procedure.
    Question 03All questionsQuestion 05

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...HardQ06A project manager takes over a high-performing agile team. The previous PM was very directive. Th...Hard
    View all 60 questions →