PMP · Question 05 · Task 1: Manage conflict
A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the project manager during a status meeting. The team is present and looks uncomfortable. What is the BEST response?
Answer options:
Defend the team's performance with data to prove the stakeholder wrong.
Remain calm, acknowledge the stakeholder's frustration, and propose a separate meeting to address their concerns.
Ask the stakeholder to leave the meeting immediately due to unprofessional behavior.
Ignore the aggression and continue with the status report presentation.
60 questions · hints · full answers · grading