PMP · Question 23 · Task 5: Ensure team members/stakeholders are adequately trained

To determine if training was effective, a project manager measures the results. According to the Kirkpatrick Model, the highest level of evaluation which measures the business impact is Level ________.

How to approach this question

Enter the number (1, 2, 3, or 4).

Full Answer

4
Kirkpatrick Level 4 is Results (Business Impact). Level 1=Reaction, 2=Learning, 3=Behavior.

Common mistakes

Confusing Level 3 (Behavior change) with Level 4 (Business Results).