Hard1 markMultiple Choice
PMP · Question 22 · Task 5: Ensure team members/stakeholders are adequately trained
A stakeholder is resisting the adoption of a new project management tool, claiming it is too difficult to use. The PM suspects this is due to a lack of training. What should the PM do?
A stakeholder is resisting the adoption of a new project management tool, claiming it is too difficult to use. The PM suspects this is due to a lack of training. What should the PM do?
Answer options:
A.
Send the stakeholder the user manual via email.
B.
Assess the stakeholder's specific learning needs and arrange a targeted walkthrough or training session.
C.
Tell the stakeholder that use of the tool is mandatory.
D.
Revert to the old tool for this stakeholder only.
How to approach this question
Identify the resistance source (lack of skill) and provide the solution (training/support).
Full Answer
B.Assess the stakeholder's specific learning needs and arrange a targeted walkthrough or training session.✓ Correct
B
The PM should validate the training need. Providing targeted support removes the barrier to adoption and builds the relationship.
Common mistakes
Choosing A (Manual). Manuals are rarely read by resistant users.
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard