Hard1 markMultiple Choice

PMP · Question 21 · Task 5: Ensure team members/stakeholders are adequately trained

A project manager identifies a skills gap in the team regarding risk management. The budget for external training is zero. Which TWO options are viable?

Answer options:

A.

Ignore the gap and hope no risks occur.

B.

Create a lunch-and-learn series where the PM or a knowledgeable senior member teaches the concepts.

C.

Pay for training out of the team party fund.

D.

Utilize free online resources and MOOCs to create a self-study curriculum.

E.

Submit a change request to increase the budget.

How to approach this question

Select creative, zero-cost solutions.

Full Answer

B,D
When budget is a constraint, the PM must be creative. Internal knowledge sharing (Lunch-and-learn) and curated free resources are effective, zero-cost ways to train.

Common mistakes

Giving up (A) or trying to get money that isn't there (E).