    Hard1 markMultiple Choice
    Task 5: Ensure team members/stakeholders are adequately trainedTrainingCost Management

    PMP · Question 21 · Task 5: Ensure team members/stakeholders are adequately trained

    A project manager identifies a skills gap in the team regarding risk management. The budget for external training is zero. Which TWO options are viable?

    Answer options:

    A.

    Ignore the gap and hope no risks occur.

    B.

    Create a lunch-and-learn series where the PM or a knowledgeable senior member teaches the concepts.

    C.

    Pay for training out of the team party fund.

    D.

    Utilize free online resources and MOOCs to create a self-study curriculum.

    E.

    Submit a change request to increase the budget.

    How to approach this question

    Select creative, zero-cost solutions.

    Full Answer

    When budget is a constraint, the PM must be creative. Internal knowledge sharing (Lunch-and-learn) and curated free resources are effective, zero-cost ways to train.

    Common mistakes

    Giving up (A) or trying to get money that isn't there (E).
    Question 20All questionsQuestion 22

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →