PMP · Question 21 · Task 5: Ensure team members/stakeholders are adequately trained
A project manager identifies a skills gap in the team regarding risk management. The budget for external training is zero. Which TWO options are viable?
Answer options:
Ignore the gap and hope no risks occur.
Create a lunch-and-learn series where the PM or a knowledgeable senior member teaches the concepts.
Pay for training out of the team party fund.
Utilize free online resources and MOOCs to create a self-study curriculum.
Submit a change request to increase the budget.