    PracticePMI PMP®PMP People Domain Practice ExamQuestion 20
    Hard1 markMultiple Choice
    Task 5: Ensure team members/stakeholders are adequately trainedTrainingResource Management

    PMP · Question 20 · Task 5: Ensure team members/stakeholders are adequately trained

    A project manager is planning a project that requires a new programming language. The team has no experience with it. The deadline is fixed and aggressive. What is the BEST training strategy?

    Answer options:

    A.

    Send the entire team to a week-long offsite bootcamp.

    B.

    Ask team members to read books on the language in their spare time.

    C.

    Hire a consultant to embed with the team and provide on-the-job coaching and code reviews.

    D.

    Request to change the programming language to one the team knows.

    How to approach this question

    Balance the need for training with the constraint of time. On-the-job training is often best for deadlines.

    Full Answer

    C.Hire a consultant to embed with the team and provide on-the-job coaching and code reviews.✓ Correct
    Embedded coaching allows for immediate application of knowledge and doesn't stop production. It addresses the competency gap without halting the project for formal training.

    Common mistakes

    Choosing A (Bootcamp). While good, losing a week on a tight deadline is risky.
    Question 19All questionsQuestion 21

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard