Hard1 markMultiple Choice
PMP · Question 19 · Task 4: Empower team members
A project manager observes that a team member, who is excellent at data analysis, is struggling with a task requiring public speaking and stakeholder negotiation. The task is critical. What should the PM do?
A project manager observes that a team member, who is excellent at data analysis, is struggling with a task requiring public speaking and stakeholder negotiation. The task is critical. What should the PM do?
Answer options:
A.
Force the team member to complete the task to build character.
B.
Reassign the task to a team member with strong communication skills and assign the analyst a complex data task.
C.
Send the analyst to a public speaking course and wait for them to finish.
D.
Do the presentation yourself.
How to approach this question
Look for the answer that aligns tasks with individual strengths.
Full Answer
B.Reassign the task to a team member with strong communication skills and assign the analyst a complex data task.✓ Correct
B
Empowerment involves organizing around strengths. Forcing someone to do something they are weak at for a critical task is poor management. Swapping tasks optimizes the team's output.
Common mistakes
Thinking 'fixing weaknesses' (C) is always the priority. In critical execution, leveraging strengths is better.
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert