PMP · Question 19 · Task 4: Empower team members
A project manager observes that a team member, who is excellent at data analysis, is struggling with a task requiring public speaking and stakeholder negotiation. The task is critical. What should the PM do?
Answer options:
Force the team member to complete the task to build character.
Reassign the task to a team member with strong communication skills and assign the analyst a complex data task.
Send the analyst to a public speaking course and wait for them to finish.
Do the presentation yourself.