    PracticePMI PMP®PMP People Domain Practice ExamQuestion 18
    Hard1 markMultiple Choice
    Task 4: Empower team membersEmpowermentDecision Making

    PMP · Question 18 · Task 4: Empower team members

    A project manager needs to make a decision about a change in the project management information system. The change affects the daily work of all team members. Which decision-making style is MOST appropriate to ensure buy-in?

    Answer options:

    A.

    Command

    B.

    Consultative

    C.

    Consensus

    D.

    Random/Coin Flip

    How to approach this question

    Match the goal (buy-in) to the style. Consensus generates the highest commitment.

    Full Answer

    C.Consensus✓ Correct
    C
    For decisions affecting daily work habits, Consensus is best because it ensures everyone is heard and agrees to support the outcome, reducing resistance to change.

    Common mistakes

    Choosing Consultative (B). While good, Consensus is better for 'buy-in'.
    Question 17All questionsQuestion 19

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →