PMP · Question 17 · Task 4: Empower team members
A team member complains that they are unsure what they are responsible for versus what the project manager handles. Which TWO documents/tools should the PM utilize to clarify this?
Answer options:
RACI Matrix
Project Schedule
Team Charter
Risk Register
Stakeholder Register