Hard1 markMultiple Choice
PMP · Question 16 · Task 4: Empower team members
A project manager is leading a large project with multiple workstreams. The PM is overwhelmed by the volume of minor decisions required daily. What is the MOST effective way to address this?
A project manager is leading a large project with multiple workstreams. The PM is overwhelmed by the volume of minor decisions required daily. What is the MOST effective way to address this?
Answer options:
A.
Work longer hours to ensure all decisions are made correctly.
B.
Establish clear decision-making thresholds and delegate authority to workstream leads.
C.
Ask the sponsor to make the minor decisions.
D.
Implement a voting system for all decisions.
How to approach this question
Identify the problem (bottleneck) and the solution (delegation/empowerment).
Full Answer
B.Establish clear decision-making thresholds and delegate authority to workstream leads.✓ Correct
B
Empowering the team involves defining boundaries (thresholds) within which they have autonomy. This is efficient and developmental.
Common mistakes
Thinking the PM must make all decisions to maintain control (A).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert