Hard1 markMultiple Choice
Task 4: Empower team membersEmpowermentPredictive

PMP · Question 16 · Task 4: Empower team members

A project manager is leading a large project with multiple workstreams. The PM is overwhelmed by the volume of minor decisions required daily. What is the MOST effective way to address this?

Answer options:

A.

Work longer hours to ensure all decisions are made correctly.

B.

Establish clear decision-making thresholds and delegate authority to workstream leads.

C.

Ask the sponsor to make the minor decisions.

D.

Implement a voting system for all decisions.

How to approach this question

Identify the problem (bottleneck) and the solution (delegation/empowerment).

Full Answer

B.Establish clear decision-making thresholds and delegate authority to workstream leads.✓ Correct
B
Empowering the team involves defining boundaries (thresholds) within which they have autonomy. This is efficient and developmental.

Common mistakes

Thinking the PM must make all decisions to maintain control (A).