An agile team asks the project manager to assign tasks to them during sprint planning because they are used to a directive environment. How should the PM respond?
An agile team asks the project manager to assign tasks to them during sprint planning because they are used to a directive environment. How should the PM respond?
Answer options:
A.
Assign the tasks as requested to maintain velocity.
B.
Refuse and tell them they must figure it out themselves.
C.
Facilitate the planning session to help them volunteer for tasks based on priority and skills.
D.
Ask the Product Owner to assign the tasks.
How to approach this question
The goal is self-organization. The PM acts as a facilitator, not a manager.
Full Answer
C.Facilitate the planning session to help them volunteer for tasks based on priority and skills.✓ Correct
C
In Agile, teams self-assign work (pull system). If they are hesitant, the PM facilitates the conversation to encourage them to take ownership, rather than reverting to command-and-control.
Common mistakes
Assigning tasks (A) to save time.
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert