Hard1 markMultiple Choice
PMP · Question 14 · Task 3: Support team performance
During a project, the team realizes they lack the specific technical skills required for an upcoming critical task. The timeline does not allow for external hiring. What is the BEST course of action?
During a project, the team realizes they lack the specific technical skills required for an upcoming critical task. The timeline does not allow for external hiring. What is the BEST course of action?
Answer options:
A.
Proceed with the current team and hope they learn on the job.
B.
Arrange for pair programming or internal cross-training with a subject matter expert from another department.
C.
Outsource the task to a vendor immediately.
D.
Update the risk register and accept the likely delay.
How to approach this question
Look for the internal solution that addresses the skill gap actively.
Full Answer
B.Arrange for pair programming or internal cross-training with a subject matter expert from another department.✓ Correct
B
Cross-training or pairing is a fast, effective way to upskill a team when hiring isn't an option. It promotes knowledge sharing and team resilience.
Common mistakes
Choosing outsourcing (C) which might be blocked by budget or procurement time.
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard