Hard1 markMultiple Choice
PMP · Question 25 · Task 6: Build a team
A newly formed team is arguing about roles and the project approach. Productivity is low. The sponsor is concerned. How should the PM explain this to the sponsor?
A newly formed team is arguing about roles and the project approach. Productivity is low. The sponsor is concerned. How should the PM explain this to the sponsor?
Answer options:
A.
Admit that the hiring process failed and request new team members.
B.
Explain that the team is in the 'Storming' stage of development, which is necessary for them to reach high performance.
C.
Promise to implement stricter rules to stop the arguing.
D.
Ignore the behavior and tell the sponsor everything is fine.
How to approach this question
Identify the Tuckman stage (Storming) and normalize it.
Full Answer
B.Explain that the team is in the 'Storming' stage of development, which is necessary for them to reach high performance.✓ Correct
B
The Tuckman model (Forming, Storming, Norming, Performing) predicts conflict in the second stage. The PM should protect the team by explaining this is a natural, temporary phase.
Common mistakes
Thinking conflict is always bad (C) or a sign of failure (A).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert