Hard1 markMultiple Choice

PMP · Question 31 · Task 7: Address and remove impediments, obstacles, and blockers for the team

A team member is blocked because they are waiting for a software license approval from the finance department. The request has been pending for a week. The PM knows the Finance Director personally. What is the BEST approach?

Answer options:

A.

Wait for the process to complete naturally.

B.

Buy the license on a personal credit card.

C.

Leverage the personal network to follow up with the Finance Director and expedite the approval.

D.

Tell the team member to use a pirated version temporarily.

How to approach this question

Look for the answer that uses 'soft skills' or 'influence' to solve a process problem.

Full Answer

C.Leverage the personal network to follow up with the Finance Director and expedite the approval.✓ Correct
C
Task 7 specifically mentions 'Use network to implement solutions'. The PM should use their influence to unblock the team without violating policy.

Common mistakes

Being passive (A) or bypassing rules (B/D).