    PracticePMI PMP®PMP People Domain Practice ExamQuestion 30
    Hard1 markMultiple Choice
    Task 7: Address and remove impediments, obstacles, and blockers for the teamImpedimentsCompliance

    PMP · Question 30 · Task 7: Address and remove impediments, obstacles, and blockers for the team

    A regulatory change has just been announced that blocks the release of the product. The team is unsure how to interpret the new regulation. Which TWO actions should the PM take?

    Answer options:

    A.

    Ignore the regulation as the project started before it was announced.

    B.

    Ask the developers to read the legal text and interpret it.

    C.

    Engage the legal department or external consultants to provide a clear interpretation.

    D.

    Facilitate a meeting between the legal experts and the team to define the necessary changes.

    E.

    Pause the project indefinitely.

    How to approach this question

    Select actions that bring in the right expertise to remove the blocker.

    Full Answer

    The PM uses their network (Legal Dept) to remove the impediment (lack of clarity). Facilitating the transfer of this interpretation to the team ensures the blocker is removed effectively.

    Common mistakes

    Asking the team to do something outside their skill set (B).
    Question 29All questionsQuestion 31

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →