PMP · Question 29 · Task 7: Address and remove impediments, obstacles, and blockers for the team
A project team identifies five distinct impediments during a meeting. Resources are limited. How should the PM determine which impediment to address first?
Answer options:
Address the easiest one first to show progress.
Prioritize based on the impact to the project's critical path and objectives.
Ask the sponsor to choose.
Assign one impediment to each team member.