    PracticePMI PMP®PMP People Domain Practice ExamQuestion 29
    Hard1 markMultiple Choice
    Task 7: Address and remove impediments, obstacles, and blockers for the teamImpedimentsPrioritization

    PMP · Question 29 · Task 7: Address and remove impediments, obstacles, and blockers for the team

    A project team identifies five distinct impediments during a meeting. Resources are limited. How should the PM determine which impediment to address first?

    Answer options:

    A.

    Address the easiest one first to show progress.

    B.

    Prioritize based on the impact to the project's critical path and objectives.

    C.

    Ask the sponsor to choose.

    D.

    Assign one impediment to each team member.

    How to approach this question

    Prioritization is always based on value/impact/risk.

    Full Answer

    B.Prioritize based on the impact to the project's critical path and objectives.✓ Correct
    Impediments should be prioritized like risks or requirements: based on their impact on the project goals (Critical Path, Cost, Quality).

    Common mistakes

    Choosing 'Easiest first' (A).
    Question 28All questionsQuestion 30

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard