Hard1 markMultiple Choice
PMP · Question 46 · Task 11: Engage and support virtual teams
A project manager leads a team across three time zones: London, New York, and Tokyo. The Tokyo team complains they always have to stay late for meetings. What should the PM do?
A project manager leads a team across three time zones: London, New York, and Tokyo. The Tokyo team complains they always have to stay late for meetings. What should the PM do?
Answer options:
A.
Keep the time as is; majority rules.
B.
Rotate the meeting times so the inconvenience is shared equally among all locations.
C.
Hold separate meetings for each region.
D.
Cancel all synchronous meetings.
How to approach this question
Look for the 'Fairness' option in global scenarios.
Full Answer
B.Rotate the meeting times so the inconvenience is shared equally among all locations.✓ Correct
B
In global teams, no single time works for everyone. Rotating meeting times demonstrates respect and fairness, ensuring no single group always bears the burden.
Common mistakes
Favoring the HQ or majority (A).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert