    PracticePMI PMP®PMP People Domain Practice ExamQuestion 47
    Hard1 markMultiple Choice
    Task 11: Engage and support virtual teamsVirtual TeamsTrust

    PMP · Question 47 · Task 11: Engage and support virtual teams

    Which TWO practices are most effective for building trust in a newly formed virtual team?

    Answer options:

    A.

    Create a 'team face book' with photos and personal bios.

    B.

    Monitor keystrokes to ensure everyone is working.

    C.

    Focus strictly on work tasks in all communications.

    D.

    Establish a virtual 'open door' policy or office hours for informal chats.

    E.

    Prohibit non-work discussions on the chat channel.

    How to approach this question

    Select options that 'humanize' the experience.

    Full Answer

    Virtual teams suffer from a lack of social context. Sharing personal info (A) and allowing for informal access (D) helps build the 'swift trust' needed for performance.

    Common mistakes

    Thinking strict control (B/C/E) builds performance. It kills trust.
    Question 46All questionsQuestion 48

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →