PMP · Question 54 · Task 13: Mentor relevant stakeholders
A project manager notices that a client stakeholder is struggling to understand the agile reporting metrics (Burnup charts). This is causing anxiety and excessive email queries. What is the BEST mentoring opportunity here?
Answer options:
Switch to traditional status reports to make them comfortable.
Tell the stakeholder to read the Agile Practice Guide.
Schedule a session to explain the charts and how they provide transparency, mentoring the stakeholder on agile concepts.
Ignore the emails.