    PracticePMI PMP®PMP People Domain Practice ExamQuestion 57
    Hard1 markMultiple Choice
    Task 14: Promote team performance through the application of emotional intelligenceEmotional IntelligenceLeadership

    PMP · Question 57 · Task 14: Promote team performance through the application of emotional intelligence

    A project manager feels a surge of anger when a stakeholder criticizes the project publicly. The PM takes a deep breath, pauses, and chooses to ask a clarifying question instead of snapping back. Which EI component is this?

    Answer options:

    A.

    Self-Awareness

    B.

    Self-Management (Self-Regulation)

    C.

    Social Awareness

    D.

    Relationship Management

    How to approach this question

    Identify the internal action: Feeling = Awareness. Acting/Controlling = Management.

    Full Answer

    B.Self-Management (Self-Regulation)✓ Correct
    Self-management is the ability to control or redirect disruptive impulses and moods. The pause and choice to respond constructively is the hallmark of self-regulation.

    Common mistakes

    Confusing Awareness (feeling it) with Management (controlling it).
    Question 56All questionsQuestion 58

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →