    PracticePMI PMP®PMP People Domain Practice ExamQuestion 60
    Hard1 markMultiple Choice
    Task 14: Promote team performance through the application of emotional intelligenceEmotional IntelligenceTools

    PMP · Question 60 · Task 14: Promote team performance through the application of emotional intelligence

    A project manager uses personality assessments (e.g., MBTI, DiSC) with the team. What is the PRIMARY purpose of this in the context of the People Domain?

    Answer options:

    A.

    To screen out personality types that don't fit the culture.

    B.

    To label team members so the PM knows who to blame for conflicts.

    C.

    To understand diverse communication and work styles, enabling better collaboration and conflict reduction.

    D.

    To determine salaries.

    How to approach this question

    Assessments are for understanding and adaptation, not selection or judgment.

    Full Answer

    C.To understand diverse communication and work styles, enabling better collaboration and conflict reduction.✓ Correct
    C
    Task 14 mentions 'Assess behavior through the use of personality indicators'. The purpose is to build self and social awareness, allowing the team to adapt their communication styles to work better together.

    Common mistakes

    Thinking assessments are for hiring/firing (A).
    Question 59All questions

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →