PMP · Question 16 · Task 5: Plan and manage budget and resources
A project has a Budget at Completion (BAC) of $100,000. Currently, the Earned Value (EV) is $40,000 and the Actual Cost (AC) is $50,000. The project manager expects the current cost performance to continue for the remainder of the project. What is the Estimate at Completion (EAC)? (Enter the number only, no currency symbols)
60 questions · hints · full answers · grading