    Hard1 markMultiple Choice
    Task 4: Engage stakeholdersTask 4AgileRoles

    PMP · Question 15 · Task 4: Engage stakeholders

    In an agile project, the Product Owner (PO) is frequently changing priorities during the sprint, causing the team to lose focus. The team is frustrated. What is the BEST action for the project manager (acting as Scrum Master)?

    Answer options:

    A.

    Allow the changes but extend the sprint duration.

    B.

    Direct the team to ignore the PO's requests until the next planning meeting.

    C.

    File a change request for every new priority.

    D.

    Coach the PO on the importance of sprint stability and the cost of context switching.

    How to approach this question

    Identify the servant-leader action: coaching and protecting the team.

    Full Answer

    D.Coach the PO on the importance of sprint stability and the cost of context switching.✓ Correct
    The PM/Scrum Master protects the team from outside interference during the sprint. The correct approach is to educate (coach) the PO on agile principles (Task 4 & Task 16).

    Common mistakes

    A (breaking timebox) is a cardinal sin in Scrum.
    Question 14All questionsQuestion 16

    Practice the full PMP Process Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
    View all 60 questions →