Hard1 markMultiple Choice
PMP · Question 14 · Task 4: Engage stakeholders
A project manager is leading a large transformation project. Several functional managers are resistant because they fear losing control over their resources. Which strategies should the project manager employ to engage these stakeholders? (Select TWO)
A project manager is leading a large transformation project. Several functional managers are resistant because they fear losing control over their resources. Which strategies should the project manager employ to engage these stakeholders? (Select TWO)
Answer options:
A.
Send them the project charter to prove the PM's authority.
B.
Exclude them from decision-making to prevent obstruction.
C.
Involve them in the resource planning process to address their concerns.
D.
Report their resistance to the CEO immediately.
E.
Focus on the benefits of the transformation for their specific departments.
F.
Use the risk register to document them as threats.
How to approach this question
Select strategies that build trust and alignment rather than using force or authority.
Full Answer
C,E
Task 4 requires executing engagement strategies. Involving resistant stakeholders (C) and highlighting benefits relevant to them (E) are proven change management techniques.
Common mistakes
Using authority (A) or escalation (D) as a first response.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert