Hard1 markMultiple Choice
Task 4: Engage stakeholdersTask 4StakeholdersModels

PMP · Question 13 · Task 4: Engage stakeholders

Using a Power/Interest Grid, a project manager identifies a stakeholder with High Power but Low Interest. What is the appropriate engagement strategy?

Answer options:

A.

Manage Closely

B.

Keep Satisfied

C.

Keep Informed

D.

Monitor

How to approach this question

Recall the 4 quadrants of the Power/Interest grid.

Full Answer

B.Keep Satisfied✓ Correct
High Power stakeholders must be managed carefully. If they have Low Interest, you don't overwhelm them with data (Keep Informed), but you ensure their needs are met so they don't use their power negatively (Keep Satisfied).

Common mistakes

Confusing 'Keep Satisfied' with 'Manage Closely'.

Practice the full PMP Process Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam