PMP · Question 24 · Task 7: Plan and manage quality of products/deliverables
A project team is performing a 'Quality Audit' to determine if project activities comply with organizational policies. Which process is this?
Answer options:
Control Quality
Manage Quality
Plan Quality Management
Validate Scope