Hard1 markMultiple Choice
PMP · Question 24 · Task 7: Plan and manage quality of products/deliverables
A project team is performing a 'Quality Audit' to determine if project activities comply with organizational policies. Which process is this?
A project team is performing a 'Quality Audit' to determine if project activities comply with organizational policies. Which process is this?
Answer options:
A.
Control Quality
B.
Manage Quality
C.
Plan Quality Management
D.
Validate Scope
How to approach this question
Distinguish between Process (Manage Quality) and Product (Control Quality).
Full Answer
B.Manage Quality✓ Correct
B
Task 7 involves managing quality. Audits are a tool of Manage Quality (QA) to ensure the right processes are being followed. Inspections are a tool of Control Quality (QC) to check the product.
Common mistakes
Confusing QA (Process) with QC (Product).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert