Hard1 markMultiple Choice
PMP · Question 25 · Task 7: Plan and manage quality of products/deliverables
Which of the following are costs of conformance (money spent to avoid failures)? (Select TWO)
Which of the following are costs of conformance (money spent to avoid failures)? (Select TWO)
Answer options:
A.
Training
B.
Warranty work
C.
Testing/Inspection
D.
Rework
E.
Scrap
F.
Liability claims
How to approach this question
Identify costs incurred *before* a failure is found by the customer (Prevention + Appraisal).
Full Answer
A,C
Cost of Quality includes Conformance (Prevention, Appraisal) and Non-conformance (Internal/External Failure). Training and Testing are proactive investments.
Common mistakes
Thinking Testing is a failure cost. It is an appraisal cost (Conformance).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert