Hard1 markMultiple Choice

PMP · Question 25 · Task 7: Plan and manage quality of products/deliverables

Which of the following are costs of conformance (money spent to avoid failures)? (Select TWO)

Answer options:

A.

Training

B.

Warranty work

C.

Testing/Inspection

D.

Rework

E.

Scrap

F.

Liability claims

How to approach this question

Identify costs incurred *before* a failure is found by the customer (Prevention + Appraisal).

Full Answer

A,C
Cost of Quality includes Conformance (Prevention, Appraisal) and Non-conformance (Internal/External Failure). Training and Testing are proactive investments.

Common mistakes

Thinking Testing is a failure cost. It is an appraisal cost (Conformance).