PMP · Question 38 · Task 10: Manage project changes
A project manager receives a change request. Before approving or rejecting it, what must be done?
A project manager receives a change request. Before approving or rejecting it, what must be done?
Answer options:
A.
Update the project schedule.
B.
Analyze the impact on scope, schedule, cost, quality, and risk.
C.
Consult the project sponsor.
D.
Implement a prototype.
How to approach this question
The 'First Step' rule: Analyze before acting.
Full Answer
B.Analyze the impact on scope, schedule, cost, quality, and risk.✓ Correct
B
Task 10: Determine strategy to handle change. Analysis is the core of the change management process.
Common mistakes
Going straight to the decision maker without the data.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert