A project manager receives a change request. Before approving or rejecting it, what must be done?

Answer options:

A.

Update the project schedule.

B.

Analyze the impact on scope, schedule, cost, quality, and risk.

C.

Consult the project sponsor.

D.

Implement a prototype.

How to approach this question

The 'First Step' rule: Analyze before acting.

Full Answer

B.Analyze the impact on scope, schedule, cost, quality, and risk.✓ Correct
B
Task 10: Determine strategy to handle change. Analysis is the core of the change management process.