Hard1 markMultiple Choice
PMP · Question 37 · Task 10: Manage project changes
During a sprint, the Product Owner asks a developer to swap a story in the current sprint for a new, higher-priority story of equal size. What should the developer do?
During a sprint, the Product Owner asks a developer to swap a story in the current sprint for a new, higher-priority story of equal size. What should the developer do?
Answer options:
A.
Make the swap immediately.
B.
Reject the request.
C.
Ask the Project Manager for permission.
D.
Refer the Product Owner to the Scrum Master or discuss it with the team.
How to approach this question
Protect the sprint, but respect the team's self-organization.
Full Answer
D.Refer the Product Owner to the Scrum Master or discuss it with the team.✓ Correct
D
Task 10 in agile: The Sprint Backlog belongs to the team. The PO cannot unilaterally change it once the sprint starts. The Scrum Master protects the team, or the team decides collectively.
Common mistakes
Thinking the PO has authority over the *current* sprint (they have authority over the *Product* backlog).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert