PMP · Question 36 · Task 10: Manage project changes
In a hybrid project, the hardware team (predictive) and software team (agile) face a scope change that affects both. How should this be handled? (Select TWO)
Answer options:
The software team implements it immediately; the hardware team waits for CCB.
The hardware impact is processed through the formal Change Control Board.
The software team rejects the change because the sprint has started.
The Project Manager approves the change for both teams.
The software impact is added to the product backlog for prioritization by the Product Owner.
Both teams switch to Kanban to manage the flow.