Hard1 markMultiple Choice
Task 10: Manage project changesTask 10HybridChange Management

PMP · Question 36 · Task 10: Manage project changes

In a hybrid project, the hardware team (predictive) and software team (agile) face a scope change that affects both. How should this be handled? (Select TWO)

Answer options:

A.

The software team implements it immediately; the hardware team waits for CCB.

B.

The hardware impact is processed through the formal Change Control Board.

C.

The software team rejects the change because the sprint has started.

D.

The Project Manager approves the change for both teams.

E.

The software impact is added to the product backlog for prioritization by the Product Owner.

F.

Both teams switch to Kanban to manage the flow.

How to approach this question

Apply the correct change process to the correct part of the project (Formal for Predictive, Backlog for Agile).

Full Answer

B,E
Task 10 involves executing change strategy. Hybrid requires a dual approach: formal CCB for the predictive side (B) and Backlog prioritization for the agile side (E).

Common mistakes

Applying one rule to both sides.

Practice the full PMP Process Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam