PMP · Question 35 · Task 10: Manage project changes
A client submits a change request to add a new module. The project manager analyzes the request and determines it will cost $10,000 and delay the project by 2 weeks. What should the project manager do NEXT?
Answer options:
Implement the change.
Update the project baseline.
Submit the change request and analysis to the Change Control Board (CCB).
Ask the team to find a way to do it for free.
60 questions · hints · full answers · grading