For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMP Process Domain Practice ExamQuestion 35
    Hard1 markMultiple Choice
    Task 10: Manage project changesTask 10Change ManagementPredictive

    PMP · Question 35 · Task 10: Manage project changes

    A client submits a change request to add a new module. The project manager analyzes the request and determines it will cost $10,000 and delay the project by 2 weeks. What should the project manager do NEXT?

    Answer options:

    A.

    Implement the change.

    B.

    Update the project baseline.

    C.

    Submit the change request and analysis to the Change Control Board (CCB).

    D.

    Ask the team to find a way to do it for free.

    How to approach this question

    Follow the sequence: Request -> Analyze -> Approve (CCB) -> Update Baseline -> Implement.

    Full Answer

    C.Submit the change request and analysis to the Change Control Board (CCB).✓ Correct
    Task 10 involves managing changes. The sequence is strict in predictive: 1. Identify 2. Analyze 3. Approve (CCB) 4. Update Plan 5. Implement.

    Common mistakes

    Skipping to implementation or baseline update before approval.
    Question 34All questionsQuestion 36

    Practice the full PMP Process Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
    View all 60 questions →