Hard1 markMultiple Choice
PMP · Question 35 · Task 10: Manage project changes
A client submits a change request to add a new module. The project manager analyzes the request and determines it will cost $10,000 and delay the project by 2 weeks. What should the project manager do NEXT?
A client submits a change request to add a new module. The project manager analyzes the request and determines it will cost $10,000 and delay the project by 2 weeks. What should the project manager do NEXT?
Answer options:
A.
Implement the change.
B.
Update the project baseline.
C.
Submit the change request and analysis to the Change Control Board (CCB).
D.
Ask the team to find a way to do it for free.
How to approach this question
Follow the sequence: Request -> Analyze -> Approve (CCB) -> Update Baseline -> Implement.
Full Answer
C.Submit the change request and analysis to the Change Control Board (CCB).✓ Correct
C
Task 10 involves managing changes. The sequence is strict in predictive: 1. Identify 2. Analyze 3. Approve (CCB) 4. Update Plan 5. Implement.
Common mistakes
Skipping to implementation or baseline update before approval.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert