Hard1 markMultiple Choice
Task 10: Manage project changesTask 10Change ManagementPredictive

PMP · Question 35 · Task 10: Manage project changes

A client submits a change request to add a new module. The project manager analyzes the request and determines it will cost $10,000 and delay the project by 2 weeks. What should the project manager do NEXT?

Answer options:

A.

Implement the change.

B.

Update the project baseline.

C.

Submit the change request and analysis to the Change Control Board (CCB).

D.

Ask the team to find a way to do it for free.

How to approach this question

Follow the sequence: Request -> Analyze -> Approve (CCB) -> Update Baseline -> Implement.

Full Answer

C.Submit the change request and analysis to the Change Control Board (CCB).✓ Correct
C
Task 10 involves managing changes. The sequence is strict in predictive: 1. Identify 2. Analyze 3. Approve (CCB) 4. Update Plan 5. Implement.

Common mistakes

Skipping to implementation or baseline update before approval.

Practice the full PMP Process Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam