Hard1 markMultiple Choice
PMP · Question 34 · Task 9: Integrate project planning activities
A project manager is planning a release for a complex product with multiple dependencies across three agile teams. Which activities will help integrate the planning? (Select TWO)
A project manager is planning a release for a complex product with multiple dependencies across three agile teams. Which activities will help integrate the planning? (Select TWO)
Answer options:
A.
Conducting a Scrum of Scrums meeting.
B.
Creating a detailed Gantt chart for all teams.
C.
Merging all teams into one large team.
D.
Holding a joint release planning session.
E.
Assigning a separate project manager to each team.
F.
Delaying the start of Team B until Team A finishes.
How to approach this question
Select scaling/coordination mechanisms suitable for agile.
Full Answer
A,D
Task 9 involves consolidating plans. In agile scaling, Scrum of Scrums (A) and Joint Planning (D) are the standard integration techniques.
Common mistakes
Applying predictive tools (Gantt) to agile scaling.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard